Construction Projects

Fairview Creek Project – This page will have updates to the Fairview Creek Project.

_______________________________________________________________

ASPHALT OVERLAY

4.10.24 – Several areas near downtown will be milled and then overlaid with asphalt. This project is set to begin the week of May 6 and residents should expect temporary lane closures as work progresses.

Areas affected: Vine Street from 1st to 3rd, 1st Street from Locust to Walnut, Coolidge Street from Walnut to Vine & Walnut Street from Coolidge to Tyson – Asphalt Project Map

Notices will be sent to affected property owners and businesses as dates are finalized.

RED BUD AVE

City Council is aware of several complaints regarding Red Bud Ave, we are working with Eagle Engineering regarding a plan to repair this stretch of road. We will post more updates as they become available.

3.8.2024 – Council approved Eagle Engineering to move forward on this project, they will be requesting bids and setting a public hearing for the bid-letting.  We hope to have construction started in fall of 2024, but it will depend on contractor availability. Due to the higher than anticipated estimated costs, Council will be doing some research on a possible GO Bond for this project and other smaller street projects and equipment needs within the City.

4.5.2024 – Council awarded the bid for Red Bud Ave to Bluffs Paving & Utilities in the amount of $246,398.47 at the March 26, 2024 meeting.  We are working with the contractor to set up dates for the repair.  Part of the scheduled road repairs are just outside city limits, Mills County has agreed to partner with the City on this project and cover some of the costs.

4.10.2024 – Bluffs Paving & Utilities has an opening in their schedule and are going to try to start this project the first week of May. The City is in favor of getting this project done before RAGBRAI. Jake Zimmerer w/Eagle Engineering will work with Bluffs Paving on scheduling. Once we have a start date, we will put out an update!

_____________________________________________________________

PLEASE CLICK HERE for Notice of Hearing and Letting  for LOCUST STREET ASPHALT PROJECT – DOT awarded this contract and the construction is set to being in September 2024.  DOT is funding this project via a reimbursement grant and are managing the project. Locust St is set to be repaired from Sharp St north to around N. Hazel St.

4.10.2024 – Western Engineering is looking at the possibility of starting this project before summer. There is a preconstruction meeting scheduled for April 30, the City will pass along updates as we have them.

_____________________________________________________________

11.29.2023 – West 6th Street UPDATE – The Contractors plan to have 6th Street reopened on Friday, December 8, 2023, weather permitting. The last section of roadway was poured on Tuesday, November 28, 2023.

9.8.2023 – West 6th Street Closure to begin on 9.18.2023 and expected to last several weeks. Please plan accordingly. Below is a map of the closure and a letter that was sent to affected residents along 6th Street and Maplewood Cir.

____________________________________________________

4.18.2023 COOLIDGE STREET IS NOW OPEN!

COOLIDGE STREET – 4.12.2023 UPDATE
Coolidge Street repairs are ahead of schedule, the portion from Locust St east to the bank parking lot is open for traffic! They are working on finishing touches on the section that is west of Walnut Street and it should be open soon. Then they will finish up with the section in the middle.

COOLIDGE STREET – 3.23.2023 UPDATE
The City’s Contractor, Carley Construction, is scheduled to begin construction along Coolidge Street between Locust Street & Walnut Street. The work includes removal of existing brick pavement, driveway connections, and offsite storm water. Work is expected to commence on Monday, March 27, 2023.

If you have any questions, you may call one of the following contacts for the project:

Jeff Fry – Eagle Engineering – 402-699-1095
Jake Zimmerer – Eagle Engineering – 402-399-0227
City of Glenwood Public Works – 712-527-4598

Affected property owners will be contacted by Eagle Engineering individually.

___________________________________________________

LOCUST STREET
You will see some increased activity on North Locust Street. The City was awarded a Surface Transportation Block Grant through the DOT, this grant is a 80/20 match grant. This project will include Locust Street from Sharp Street north to around North Hazel Street.  Work should be completed in FY2024. The work you are seeing now is the very first steps in getting ready to put this project out for bid.

Please click on the link below for an update on the Coolidge Street Project. The City has contacted street repairs and storm sewer installation on Coolidge Street from Locust Street to Walnut Street. As more information and definite timelines become available, we will post updates. Property owners will be notified with more information regarding definite timelines and disruptions to traffic.
Coolidge Street Repairs Update